Route 53 update

Dear fellow Hanoverians:

 

We have all dodged the cones and trucks along the =
northern/middle
portion of Route 53 for the past year and a half and work is progressing =
quite
nicely.  As someone who commutes through this portion of Route 53 =
most days, I
have to say that the project has been managed very well and delays have =
mostly
been kept to a minimum.  Good news – the Route 53 bridge over Route =
3 is about
to finally be reconstructed, too.  Hooray!  More delays, but =
all for the
eventual good.  Below please find an update from the Planning =
Department
regarding both of those projects, with special thanks to Andy Port, Town =
Planner:

 

Route 53 (Washington =
Street)
/ Route 3 Bridge:
=

 

In mid-August 2009, the =
Massachusetts
Highway Department (MHD), through their consultant contractor (Aetna =
Bridge
Company) will re-start work on the long-awaited reconstruction of the
Washington Street (Route 53) over Route 3 bridge.  The anticipated
completion date for this project is July, 2012.  The location of =
this
project is shown on the map above.

 

The Bridge crossing will remain OPEN =
during
construction.  MassHighway and the Town ask for patience from the =
public
as this important traffic improvement project is underway.  =
However, there
may be some delays due to limited lane width and work space.  As =
such we
anticipate that residents, businesses, commuters, and the general public =
will
consider alternative routes as they deem =
necessary.

 

Route 53 (Washington =
Street)
Roadway Widening:
=

 

Since April 2008, the Massachusetts =
Highway
Department (MHD), through their consultant contractor (Paolini =
Corporation) has
been widening an approximately one-mile length of Washington Street =
(Route 53)
in Hanover.  The limits of this widening project are between Mill =
Street
and Pond Street/Rawson Road.

 

Between August 4 & 7, 2009 the
contractor will be conducting final paving operations on the northern =
section
of this stretch of road.

 

Between August 10 & 11, 2009, =
the
contractor will be installing roadway lane striping.
=

 

The remainder of the project =
(southern
roadway section) will be completed between August 2009 and October =
2010.

 

Businesses on Route 53, including =
those
along this stretch of Route 53 will remain OPEN during =
construction. 
MassHighway and the Town ask for patience from the public as this =
important
traffic improvement project is underway.  While this stretch of =
Route 53
will remain open to traffic during construction, there may be some =
delays due
to limited lane width and work space.  As such we anticipate that
residents, businesses, commuters, and the general public will consider =
alternative
routes
as they deem necessary.

 

The project, once completed, will =
provide
additional lane capacity and a middle turning lane, matching the =
alignment
along Washington Street near the Hanover Mall.  The anticipated =
completion date
for this project is October 1, 2010.

 

If you have any questions concerns =
or
complaints about work during the construction period, please contact the =
Town
of Hanover Planning Office (781-826-7641).  Detailed plans of the =
project
are available in the office for those who have concerns about the =
project other
than general questions.

 

For "Around Town on the =
Web",

Cathy H-B

 

"Around Town on the Web" is a community =
service
that has been provided to self-selected residents of the Town of Hanover =
since
the spring of 2004.  If someone forwarded this message to you and =
you would
like to receive these communications directly, please e-mail your first =
and
last name and e-mail address to cathyhb@atotw.com .  If you would =
like to be
removed from this distribution list, please e-mail your request to me at =
cathyhb@atotw.com
.  For submission guidelines and answers to frequently asked =
questions about
"ATOTW", please go to www.atotw.com